Oaxaca to Puerto Escondido
We have just returned to San Miguel from Christmas in Oaxaca. While there we heard about the great beaches in Puerto Escondido, but it was trip taking six to seven hours. The other night we met Robin and Donnie Crisp at Hecho and they raved about Puerto Escondido. It's great to read that the new highway being built will cut travel time to two hours, BUT it's behind schedule and out of money: From Mexico News Daily: When the Oaxaca governor met earlier this year with federal transportation officials and representatives of the construction firm ICA, there was optimism that two new super-highways were nearing completion.
But like previous pronouncements regarding the two massive projects, the optimism was overdone.
One of them is a 104-kilometer highway through the mountains that will provide a new link between the city of Oaxaca and the coastal city of Puerto Escondido. Construction began in 2010 and completion was slated for 2013.
That date was later amended to the end of 2014. Two months later, in February this year, Governor Gabino Cué said it would be operational by the end of 2015.
But last month, nine months after that promise, the highway was only 60% completed. The new completion date: the beginning of the third quarter of 2016.
Now, it turns out, ICA’s financial problems have thrown another wrench in the works. The state said on Saturday it was working with the federal Communications and Transportation Secretary to find the 700 million pesos needed to finish the road. ICA is no longer able to provide it.
Mexico’s largest construction company missed a US $31-million bond payment in late November and entered a 30-day grace period. Thirty days later, it defaulted.
The firm said it did so “to preserve liquidity, prioritize ongoing operations and fund projects currently under development.”
The second highway, linking Oaxaca city with the Isthmus of Tehuantepec, was reported to be 54% complete. It was scheduled to be operational during the first half of next year, but that date was amended last week to the third quarter of next year. However, there was no indication that it was facing a funding shortfall as well.
It, too, is a big project in difficult, mountainous terrain requiring 54 bridges, 11 viaducts and three tunnels over the course of the 169-kilometer route. The 9.3-billion-peso highway will reduce travel time between the state capital and the isthmus from four and a half hours to two.
While a third-quarter completion is still anticipated for the highway to the coast, that is now subject to coming up with the funds to finish it. And while the state said in November that it had resolved land ownership disputes with communities located on the route, it has said so before only to be faced with new ones.
Slated to cost 5.25 billion pesos, the highway will shorten the trip between the capital and Puerto Escondido from six or seven hours to just over two.